SBB ENERGY AND VEOLIA ENERGIA POZNAŃ ZEC HAVE SIGNED A CONTRACT FOR DENOX SYSTEM

2015-11-30

 On 24th November our company and Veolia Energia Poznań signed an agreement for the power units ECII Karolin power plant in Poznan. The end of the project is planned on 2018.

BOILER BC-50 IN TAURON CIEPŁO S.A. - THE START-UP

2015-11-24

The start-up works of boiler of the unit BC-50 in Tauron Ciepło S.A. (ZW Tychy) are succesfully ended. The whole project is planning to be finished in January 2016.

CHVALETICE-PROJECT

2015-11-20

On 20th of November 2015 was signed a contract between SBB ENERGY and KRÁLOVOPOLSKÁ RIA company. The main work will include implementation of DeNOx installation for boilers no 3 and 4 in Chvaletice Power Pland.

The end of work is planned on Novemver 2016.